For the record...

Electrician started today.

Plumber is done upstairs and will be done by next week with the lower.

My best guesses...

Estimated Insulation Install: July 26
Estimated Sheet Rock Stock: July 31
Estimated Sheet Rock Start: August 1
Estimated painting date: September 1
Estimated Trim date: September 6
Estimated Move in Date: September 22