update 7/8/06











Week 7:
The siding is done except for the shakes in the gables.
The back windows are in.
The plumber is almost finished with the plumbing, heating, cooling rough ins.
The electician hasn't started yet, maybe this next week.
I ordered the columns for the porch, dining room, and basement.
The deck footings are poured and they'll be starting on the decks next week.
Now, if I can just make some decisions on light fixtures....